Phase 1: Technical visit and quote (Day 0)
The Enclos Instal technician evaluates: floor area and layout, existing insulation, current heating system, electrical access and possible location of the outdoor unit. With this information, the thermal load is calculated and the most suitable model (Daikin, Panasonic, Vaillant or De Dietrich) and configuration is proposed.
Installation phases
- Electrical preparation (Days 1–2): dedicated electrical circuit from the main panel.
- Outdoor unit installation (Days 1–3): on anti-vibration mount, oriented south or south-east.
- Indoor hydraulic installation (Days 2–6): DHW accumulator, connection to the heating circuit, valves.
- Commissioning (final day): parameter configuration, manufacturer app setup, owner demonstration.
| Type of installation | Total time (working days) | Home liveable during works? |
|---|---|---|
| Monobloc aerothermal + DHW (renovation) | 2 – 4 days | Yes |
| Aerothermal + fan coils (150 m² renovation) | 5 – 8 days | Yes (partially) |
| Aerothermal + underfloor heating (new build) | 3 – 5 days (coordinated with works) | No (new build) |
| Aerothermal + underfloor heating (full renovation) | 15 – 30 days | No (civil works) |
Official Installers in Alt Empordà
Frequently asked questions
When can I switch on the aerothermal after installation?
Immediately. Commissioning includes starting up and verifying the system. The very day of installation it can already be used for heating, cooling and DHW.